Pre-Construction Work Underway at East Anglia Three Offshore Wind Farm Site

A pre-installation survey at the East Anglia Three offshore wind farm site is scheduled to begin in early January 2025, following subsea boulder clearance and scour protection work that was carried out in November 2024 and marked the start of offshore construction work.

The survey, which will be performed by Seaway7 and Beam using the vessel Glomar Worker, is expected to be completed by the end of January, according to a Notice to Mariners from ScottishPower Renewables.

The offshore pre-construction activities at the East Anglia Three site, located 69 kilometres off the Norfolk coast, began in early November with the relocation of boulders and non-geological debris, for which Seaway7 deployed the vessel Glomar Wave.

Around the same time, the company, in cooperation with Boskalis, mobilised the fallpipe vessel Rockpiper to install scour protection at the locations where wind turbine and offshore substation foundations will be installed.

The 1.4 GW East Anglia Three will comprise 95 Siemens Gamesa 14+ MW wind turbines, all of which are expected to be operational in 2026.

Seaway7 signed a contract in June 2023 for the transport and installation of 95 monopile foundations, associated seabed preparation and scour protection, and the engineering, supply, and installation of the inter-array cables.

Haizea Wind Group and the Navantia-Windar consortium are manufacturing the monopile foundations and transition pieces for the project, while the inter-array cables will be supplied by Hellenic Cables.

The 1.4 GW East Anglia Three is the second of ScottishPower Renewables’ East Anglia offshore wind farms to be developed and part of the East Anglia Hub which includes two other offshore wind farms: the 800 MW East Anglia One North and the 900 MW East Anglia Two.

The wind farm was awarded a Contract for Difference in July 2022 and ScottishPower, owned by Spanish Iberdrola, started onshore construction work the same month.

source: offshorewind.biz

Gallery

wind_week-177 wind_week-16 OrbisEnergy OrbisEnergy 19sqm office OrbisEnergy Meeting Room Conference Room Conference Room- Theatre style layout Conference Room

The Team

Steve Huxter - Building and Tenant Manager

Steve has recently been appointed as Building and Tenant Manager have joined OrbisEnergy as a Property Support Administrator in July 2019.

Ian Pease

Ian Pease, Business Development Manager joined in February 2020. His role is to drive forward OrbisEnergy as an innovation and technology cluster for the region’s clean energy sector by working closely with new and existing tenants.

Ashleigh Farrow - Property Support Administrator

Ashleigh is our newly appointed property support administrator who joined us in July 2024. Ashleigh is keen to learn and get acquainted with all the practices of the company.

Lauren Knowles - Property Support Administrator

Lauren has recently joined the OrbisEnergy team. Lauren is excited and looking forward to the challenges her new post will bring.

  • loading tweets...